No Changes in Work Areas, Restrictions
for Route 219 Bradford Bypass Project

Next week, no changes are scheduled for the current closures, restrictions.


Clearfield – PennDOT issues the following travel update for the Route 219/Bradford Bypass project in McKean County. This update is for the week of May 10. All work is weather and schedule dependent. Glenn O. Hawbaker, Inc. of State College is the contractor on this $28 million job.

· Northbound traffic is sharing a lane with southbound traffic, separated by temporary concrete barrier from Mill Street to north of Hillside Drive.
· Northbound ramps at Foster Brook Interchange are closed. Traffic is to follow the posted detours.
· Tuna Crossroads (T-369) is closed in order to grout new beams and install work platforms. Traffic is to follow the posted detours.
· The Tuna Valley Trail access at Bolivar Drive is closed due to bridgework. Trail access is still available at Crook Farms and Seward Avenue side of Tuna Crossroads.
· Northbound access at Kendall Avenue remains open.
· Access at Hillside Drive is restricted from Route 219 south to Hillside Drive and from Hillside Drive to Route 219 south. Traffic is to follow the posted detours.
· The contractor continues to excavate existing roadway and perform bridge repairs.
· Drivers should use extra caution while entering the construction area from the on-ramp areas. Watch for slow moving and stopped vehicles through the entire work zone and obey posted speed limits.

Comments

Popular posts from this blog

Woman Charged with Posting
Nude Picture on Facebook

Arrests in Operation Diamond Drop

Two Arrested on Drug Charges